Eco-friendly
Nowy Breń I Stage 1 - anti-filtration protection of the left embankment of the Nowy Breń River.
Nowy Breń I Stage 1 - anti-filtration protection of the left embankment of the Nowy Breń River at a length of 2,483 kilometres of the left embankment of the Nowy Breń River at km: 0+000 - 0+653 and 2+170 - 4+000 in the towns of Otałęż and Ziempniów in the Czermin Commune, in the part located in the Podkarpacie Province.
The scope of construction included as follows:
- preparation works,
- earthworks and sealing works,
- finishing works,
- service road,
- bank access roads: 6 pcs.,
- bank footing exits: 25 pcs.,
- repair of access roads,
- repair of the water-gate at 0+498 km,
- reconstruction of the water-gate at 3+765 km.
- Investor: Podkarpacki Zarząd Melioracji i Urządzeń Wodnych
- Contractor: Mostostal Warszawa S.A. / Przedsiębiorstwo Robót Geologiczno-Wiertniczych Grażyna Janik, Roman Kuś Sp. j. / Mieleckie Przedsiębiorstwo Budowlane S.A.
- Contract value: PLN 4.0 million
- Implementation period: 2009 – 2010
Contract Value: PLN 28.79 million net
Deadline for completion: 30.09.2025

Contract Value: 199.90 mln PLN gross
Deadline for completion: 33 months

Contract Value: PLN 32.1 million
Deadline for completion: 48 months


Marshal's Office of the West Pomeranian Voivodeship
MPGK Krosno Sp. z o.o.
Grudziądz Municipality

Podkarpackie Management Board of Melioration and Water Devices in Rzeszów