General
"Atmosfera Apartamenty" Housing Estate, B1 building (Wilanów B1)
Location: 17 F. Klimczak Street, Warsaw-Wilanów
The scope of work included construction of an apartment building with an underground garage, which is part of the "Atmosfera Apartamenty" complex. The building has 136 apartments; 10 commercial offices and 228 parking spaces - including 186 in the "Klaus" platform system.
Signing of the contract: 7 August 2008
Completion of the contract: 30 June 2010
- Investor: Acciona Nieruchomości Wilanów Sp. z o.o.
- Contractor: Mostostal Warszawa S.A. / Acciona Infrastructure S.A.
- Contract value: PLN 85.06 million
- Implementation period: 2008 – 2010
Contract Value: 314,6 mln PLN gross
Deadline for completion: June 30, 2028

Contract Value: PLN 24,9 mln gross
Deadline for completion: end of 2025

Contract Value: 48,85 mln EUR net
Deadline for completion: 30.09.2026

Total area: 5,966 m2
Contract Value: PLN 95.35 million gross
Deadline for completion: Within 36 months from the date of signing the contract

Contract Value: PLN 61.87 million
Deadline for completion: up to 21 months

Contract Value: PLN 130.28 million gross
Deadline for completion: June 26, 2024

Contract Value: PLN 84.99 million gross
Deadline for completion: 30 months from the date of signing the contract

Contract Value: PLN 134,80 million net
Deadline for completion: 31/01/2024

Contract Value: PLN 65,30 million net
Deadline for completion: until August 18, 2023

Deadline for completion: do 31.05.2022


Wojewódzkie Przedsiębiorstwo Usług Turystycznych Sp. z o.o.