The agreement for the realization of the taskwas signed 12 June 2006. The scope of the work involved execution of raw estate of the retail and residential building at Zwycięzców Street in Warsaw.
- Investor: Echo Investment S.A.
- Contractor: Mostostal Warszawa S.A.
- Contract value: PLN 21,23 mln
- Implementation period: 2006–2007
- Country: Poland
- Voivodeship: mazovian
Contract Value: 314,6 mln PLN gross
Deadline for completion: June 30, 2028

Contract Value: PLN 24,9 mln gross
Deadline for completion: end of 2025

Contract Value: 48,85 mln EUR net
Deadline for completion: 30.09.2026

Total area: 5,966 m2
Contract Value: PLN 95.35 million gross
Deadline for completion: Within 36 months from the date of signing the contract

Contract Value: PLN 61.87 million
Deadline for completion: up to 21 months

Contract Value: PLN 130.28 million gross
Deadline for completion: June 26, 2024

Contract Value: PLN 84.99 million gross
Deadline for completion: 30 months from the date of signing the contract

Contract Value: PLN 134,80 million net
Deadline for completion: 31/01/2024

Contract Value: PLN 65,30 million net
Deadline for completion: until August 18, 2023

Deadline for completion: do 31.05.2022


Wojewódzkie Przedsiębiorstwo Usług Turystycznych Sp. z o.o.