The agreement for the realization of the task was signed 28 May 2007. The scope of the works included core and shell of the Galeria Cuprum in Lublin. The works lastes 14 months.
Investor: MGC INWEST Sp. z o.o.
Contractor: Wrobis S.A.
Contract value: PLN 97,6 mln
Implementation period: 2007 – 2008
Country: Poland
Voivodeship: Lower Silesia
Contract Value: 314,6 mln PLN gross
Deadline for completion: June 30, 2028

Contract Value: PLN 24,9 mln gross
Deadline for completion: end of 2025

Contract Value: 48,85 mln EUR net
Deadline for completion: 30.09.2026

Total area: 5,966 m2
Contract Value: PLN 95.35 million gross
Deadline for completion: Within 36 months from the date of signing the contract

Contract Value: PLN 61.87 million
Deadline for completion: up to 21 months

Contract Value: PLN 130.28 million gross
Deadline for completion: June 26, 2024

Contract Value: PLN 84.99 million gross
Deadline for completion: 30 months from the date of signing the contract

Contract Value: PLN 134,80 million net
Deadline for completion: 31/01/2024

Contract Value: PLN 65,30 million net
Deadline for completion: until August 18, 2023

Deadline for completion: do 31.05.2022


Wojewódzkie Przedsiębiorstwo Usług Turystycznych Sp. z o.o.