Energy
Gas desulpharisation system for Ciepłownia Gliwice
The contract for the realization of the tasj was signed 12th February 2007. The scope of works included construction of two installations: one for WP-70 boilers and the second for WR-25 boilers. The installations were produced using dry scrubbing method (spray drying) based on technology of AMK Kraków.
- Investor: Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o.
- Contractor: AMK Kraków S.A.
- Contract value: PLN 46,34 mln
- Implementation period: 2007–2008
- Country: Poland
- Voivodeship: Silesia
Total area: 150,000 m3
Contract Value: 148 mln PLN
Deadline for completion: 2025

Contract Value: PLN 109,47 mln gross
Deadline for completion: 20.12.2023

Contract Value: PLN 345,63 mln gross
Deadline for completion: 30 months

Contract Value: PLN 609 million net
Deadline for completion: 33 months

Contract Value: 55 mln PLN gross
Deadline for completion: 15 months


Foster Wheeler Energia Polska Sp. z o.o. dla Elektrowni Turów
Białystok Co-Generation Plant