Ringroad Motorway in Wrocław - part II (kopia)
The agreement was signed October 22, 2008.
The consortium which realized the task formed 4 companies: Mostostal Warszawa (30% share), Strabag Sp. z o.o. – leader (30% share), Heilit+Woerner Budowlana Sp. z o.o. – partner (20%), Dywidag Bau GmbH - partner (20% share).
Investor:The General Directorate of National Roads and Motorways, Branch Wrocław
Contractor: Mostostal Warszawa S.A.
Contract value: PLN 2058 mln
Implementation period: 2008-2011
Country: Poland
District: Mazovian
Contract Value: 305,79 mln PLN gross
Deadline for completion: second half of 2028

Contract Value: 4.8 million PLN net
Deadline for completion: 2024

Total area: 1393.26 m2
Contract Value: PLN 10.7 million net
Deadline for completion: 2025

Contract Value: PLN 5.4 million net
Deadline for completion: 2024

Contract Value: 14.492 mln PLN net
Deadline for completion: no later than February 14, 2024

Contract Value: PLN 1,063.25 million gross
Deadline for completion: 39 months

Contract Value: PLN 57,51 million
Deadline for completion: 33 months

Contract Value: PLN 2,230.17 million gross
Deadline for completion: 54 months

Contract Value: PLN 635,06 million
Deadline for completion: 45 months

Contract Value: 403,7 mln zł brutto
Deadline for completion: 36 miesięcy