Revitalization of public spaces in the Wadowice market square and adjacent streets together with municipal and road infrastructure
Scope of work under the contract:
- Reconstruction of the John Paul II Square involving extension of its surface, changing the shape and exchanging the surface – 4,835.00 m2
- Reconstruction of sections of streets adjacent to the square:
- Installation of small architectural elements: benches, garbage cans, a fountain, information box, a well,
- Construction of a water main,
- Construction of storm water drainage,
- Construction of a sanitary sewage system,
- Construction and protection of a power grid,
- Construction of lighting,
- Construction and protection of telecommunication networks.
Signing of the contract: 31 May 2010.
Completion of the contract: 31 October 2010
• Investor: Wadowice Commune
• Contractor: Mostostal Warszawa S.A.
• Contract value: PLN 7.24 million
• Implementation period: 2010 – 2012
Contract Value: 305,79 mln PLN gross
Deadline for completion: second half of 2028

Contract Value: 4.8 million PLN net
Deadline for completion: 2024

Total area: 1393.26 m2
Contract Value: PLN 10.7 million net
Deadline for completion: 2025

Contract Value: PLN 5.4 million net
Deadline for completion: 2024

Contract Value: 14.492 mln PLN net
Deadline for completion: no later than February 14, 2024

Contract Value: PLN 1,063.25 million gross
Deadline for completion: 39 months

Contract Value: PLN 57,51 million
Deadline for completion: 33 months

Contract Value: PLN 2,230.17 million gross
Deadline for completion: 54 months

Contract Value: PLN 635,06 million
Deadline for completion: 45 months

Contract Value: 403,7 mln zł brutto