Infrastructure
Road viaduct over Zesłańców Syberyjskich Roundabout in Warsaw
The works consisted on supporting steelwork weighing 400 tonnes, merging, assembly, metallization and corrosion protection works.
- Investor: Geberalna Dyerkcja Dróg Publicznych
- Contractor: Mostostal Kielce S.A.
- Contract value: PLN 2,6 mln
- Implementation period: 2002–2003
- Country: Poland
- Voivodeship: mazovian
Contract Value: 305,79 mln PLN gross
Deadline for completion: second half of 2028

Contract Value: 4.8 million PLN net
Deadline for completion: 2024

Total area: 1393.26 m2
Contract Value: PLN 10.7 million net
Deadline for completion: 2025

Contract Value: PLN 5.4 million net
Deadline for completion: 2024

Contract Value: 14.492 mln PLN net
Deadline for completion: no later than February 14, 2024

Contract Value: PLN 1,063.25 million gross
Deadline for completion: 39 months

Contract Value: PLN 57,51 million
Deadline for completion: 33 months

Contract Value: PLN 2,230.17 million gross
Deadline for completion: 54 months

Contract Value: PLN 635,06 million
Deadline for completion: 45 months

Contract Value: 403,7 mln zł brutto
Deadline for completion: 36 miesięcy